Ramp Work at I-44/Greene County Routes MM/B Interchange West of Springfield to Start Nov. 5

What: Ramp work at Greene County Routes MM/B off ramps at I-44 west of Springfield
 
When: Monday morning, Nov. 5 until mid-to-late November
 
Why: Raising and widening ramps to improve visibility for drivers entering Routes MM/B from I-44
 
Project Schedule/Traffic Impacts:
·         During daytime hours, drivers can expect crews and equipment close to traffic working along the eastbound and westbound off ramps
·         Starting after 9 a.m. Monday, Nov. 5, eastbound off ramp CLOSED ‘round the clock for up to two weeks
·         Starting at mid-week, westbound off ramp CLOSED at night. Work hours: 7 p.m. to 6 a.m.
·         Drivers urged to find alternate routes to get around the ramp closings including Route 360 and Route 266 (West Chestnut Expressway)
·         Entire project complete by late November
 
(Weather and/or construction delays will alter the work schedule)